10 Topics
Step 1- Develop and document control procedures
Step 2- Select and Train Employees
Step Three- Prepare Machinery
Step 4- Shut Down of Machinery
Step 5- Isolation of Source Energy
Step 6- Lock and Tag Placement
Step 7- Stored Energy Release
Step 8 – Verification
Step 9-Re-Energize
Step 10 – Document Best Practice
Who needs to comply with LOTO OSHA standards?
Final Test – Energy Isolation Lock Out/Tag Out
Advanced Safety and Training Logo
Previous Topic
Next Topic

Step 9-Re-Energize

Lock Out Tag Out – LOTO / Energy Isolation Proper Steps for Energy Isolation Step 9-Re-Energize
Lesson Progress
0% Complete

Now that the job has been completed….After technicians complete the maintenance, an authorized employee verifies that all workers are aware of the planned re-energization and that they are positioned safely on the worksite. It is also necessary to remove all tools and repair equipment. This process includes removing the tags and locks by the same person that placed them, and reenergizing the machine.

Previous Topic
Back to Lesson
Next Topic