Step 1- Develop and document control procedures
Step 2- Select and Train Employees
Step Three- Prepare Machinery
Step 4- Shut Down of Machinery
Step 5- Isolation of Source Energy
Step 6- Lock and Tag Placement
Step 7- Stored Energy Release
Step 8 – Verification
Step 9-Re-Energize
Step 10 – Document Best Practice
Who needs to comply with LOTO OSHA standards?
Final Test – Energy Isolation Lock Out/Tag Out
Previous Lesson
Next Lesson
Proper Steps for Energy Isolation
Lock Out Tag Out – LOTO / Energy Isolation
Proper Steps for Energy Isolation
Lesson Content
0% Complete
0/10 Steps
Step 1- Develop and document control procedures
Step 2- Select and Train Employees
Step Three- Prepare Machinery
Step 4- Shut Down of Machinery
Step 5- Isolation of Source Energy
Step 6- Lock and Tag Placement
Step 7- Stored Energy Release
Step 8 – Verification
Step 9-Re-Energize
Step 10 – Document Best Practice
Previous Lesson
Back to Course
Next Lesson